McINTYRE PROPERTIES BUILDING B

Address: 89 S. Danebo Avenue., Eugene, Oregon 97402

New Construction - Concrete Tilt Warehouse

Square Footage: 43,750

Construction Timeline

  • Slab Pour: April, 2nd Week

  • Panel Rebar: May, 1st Week

  • Panel Pour: May, 3rd Week

  • Building Erection: May, 4th Week

  • Site Concrete: June, 1st Week

  • Interior: June, 2rd Week

  • Paving: June, 3rd Week

  • Completion: July, 1st Week

Disciplines

  • Rebar

  • Rebar Tying

  • Concrete Placing

  • Crane & Rigging

  • Site Concrete

  • Paving

  • Landscape

  • Structural Metal

  • Wood Framing

  • Top Cap/Flashing/Gutters

  • Rollup Doors

  • Painting

  • HVAC (Design-Build)

  • Plumbing (Design-Build)

  • Fire Sprinkler

  • Fire Alarm

  • Electrical (Design-Build)

  • Low Voltage (Design-Build)

DATES OF IMPORTANCE

BID DATE: 03/18/2022

AWARDED: 03/25/2022

CONTACT INFORMATION

Project Manager:
David Adkisson
davida@mci-construct.com
(541) 687-2841 (Office)
(541) 735-0695 (Cell)


Submit Estimates to:
estimating@mci-construct.com

bottom of page