McINTYRE PROPERTIES BUILDING B
Address: 89 S. Danebo Avenue., Eugene, Oregon 97402
New Construction - Concrete Tilt Warehouse
Square Footage: 43,750
Construction Timeline
-
Slab Pour: April, 2nd Week
-
Panel Rebar: May, 1st Week
-
Panel Pour: May, 3rd Week
-
Building Erection: May, 4th Week
-
Site Concrete: June, 1st Week
-
Interior: June, 2rd Week
-
Paving: June, 3rd Week
-
Completion: July, 1st Week
Disciplines
-
Rebar
-
Rebar Tying
-
Concrete Placing
-
Crane & Rigging
-
Site Concrete
-
Paving
-
Landscape
-
Structural Metal
-
Wood Framing
-
Top Cap/Flashing/Gutters
-
Rollup Doors
-
Painting
-
HVAC (Design-Build)
-
Plumbing (Design-Build)
-
Fire Sprinkler
-
Fire Alarm
-
Electrical (Design-Build)
-
Low Voltage (Design-Build)
DATES OF IMPORTANCE
BID DATE: 03/18/2022
AWARDED: 03/25/2022
CONTACT INFORMATION
Project Manager:
David Adkisson
davida@mci-construct.com
(541) 687-2841 (Office)
(541) 735-0695 (Cell)