REQUEST FOR SUBCONTRACTOR BIDS
597 SW 150th Ave Beaverton, OR, 97006
Project Description
Rebid/Additional Bids for Interior Finishes/ Exterior Work
Drywall Note: Downstairs bathrooms, elevator & stairwells to be completed only. Exterior walls to be finished under "Portal Escape Rooms" TI.
Insulation Note: Downstairs bathrooms, elevator, Mechanical Room, Sprinkler Room, stairwells, and exterior walls to be completed only.
Paint Note: Bathrooms to be Painted, along with Exterior of Building.
Important Dates
RFI due date: 11/03/21
Bid due date: 11/10/21
Construction Start: Active
Construction End: February 2022
CSI Disciplines
CSI Div 6 (Wood + Plastics)
CSI Div 7 (Thermal + Moisture)
CSI Div 9 (Finishes)
CSI Div 15 (Plumbing)
Contact Info
Project Manager: David Adkisson
Email: davida@mci-construct.com
Phone: (541) 687-2841
Email Bids to: thetokatlybuilding@mci-construct.com